November 19, 2026
On November 9, the Alamo Heights City Council had two items on its agenda for 131 Mary D Ave. The first was Ella Bree Homes' request to demolish the house completely and build a new single-family residence. The second, Case 1057F, asked for a variance and an appeal of a staff decision under Section 5-134(b), the rule that "prohibits separation of the significance and compatibility review processes." Council approved the demolition 5 to 0. The minutes record "no action taken/necessary" on the variance because the demolition approval made it moot.
In 2026 the Architectural Review Board's process has shaped the order of the work and the calendar for teardowns on its docket.
From February through October 2026, every demolition review case that got a significance finding was declared not significant. That's fourteen cases, and the board recommended a compatible design in each one.
| Address | Scope of work | ARB recommendation | Where it stands |
|---|---|---|---|
| 280 Tuxedo Ave | About 36% of north street façade, 100% of roof | Feb. 17 | Sent to Council Mar. 9 |
| 305 Argo Ave | Full demolition | Mar. 17 | Sent to Council Apr. 13 |
| 310 Lamont Ave | Full demolition | Mar. 17 | Sent to Council Apr. 13 |
| 202 Rosemary Ave | 38.7% of west street façade, 50.1% of wall framing | Mar. 17 | Sent to Council Apr. 13 |
| 215 Morse St | Full demolition | Mar. 17 | Sent to Council Apr. 13 |
| 607 Evans Ave | Full demolition | Apr. 21 | Sent to Council May 11 |
| 217 Corona Ave | Full demolition | Jun. 16, with conditions | Recommended |
| 216 Grant Ave | New residence | Jun. 16 | Recommended |
| 126 College Blvd | Full demolition | Jun. 16, revised design | Recommended |
| 530 Corona Ave | Full demolition | Jul. 28, rescheduled from Jul. 21 | Recommended |
| 200 Primrose Pl | Full demolition | Sep. 15 | Sent to Council Sep. 28 |
| 118 Routt St | 51.62% of street-facing façade, plus addition | Oct. 20, first listed Aug. 18 | Approved by Council Nov. 9 |
| 131 Mary D Ave | Full demolition | Oct. 20, tabled Sep. 15 | Approved by Council Nov. 9 |
| 138 Corona Ave | Full demolition | Oct. 20, with conditions | Approved by Council Nov. 9 |
The applicants are builders and design firms that work in the neighborhood regularly. Hearthside Homes filed for 305 Argo and 217 Corona. Nic Abbey Homes filed for 216 Grant and for a new residence at 231 Encino Ave. Dave Isaacs Homes filed for 126 College, MSA Architecture + Interiors for 310 Lamont, and Chesney Morales Partners for 200 Primrose. Several projects were filed under LLC ownership, including 215 Morse, 607 Evans and 217 Corona. That pattern points to investment and spec-build activity as well as owner-occupant rebuilds.
Much of the board's 2026 work has gone into the design of the replacement homes, with conditions and revisions appearing repeatedly: 217 Corona and 138 Corona were recommended with conditions, 126 College with a revised design, and 215 Morse with a trellis or other softening feature that the applicant agreed to.
Section 5-134(b) of the Alamo Heights City Code states:
"The significance and compatibility process may not be completed in separate processes."
The Mary D variance request asked to separate the significance and compatibility review processes. Council resolved the case by approving the combined application.
This is general information about a public process, not legal, tax or financial advice. Confirm how these rules apply to a specific property with a real estate attorney, your architect or builder, and the city's Community Development Services staff.
The city's Demolition Review page says the process "takes about 30 days to complete, not including plan review."
In 2026, 200 Primrose reached Council 13 days after its ARB recommendation. 280 Tuxedo, 231 Encino and 607 Evans took 20 days, and the four March 17 cases took 27.
The ARB meets once a month. 118 Routt St was first listed on August 18, rescheduled from the September 15 meeting, recommended on October 20 and approved by Council on November 9, which is 83 days in all. 131 Mary D was tabled on September 15, returned with a revised proposal on October 20 and was approved on November 9, 55 days after its first listing. Neither case ended in a denial, and both took a month or two longer than the clean ones. The timeline for a teardown purchase, from rate lock and builder schedule to the cost of holding a house that is about to be demolished, can be affected by how many monthly meetings the case needs.
The 2026 docket also includes remodels. 280 Tuxedo involved about 36% of the north street façade and the entire roof. 118 Routt was an addition that removed 51.62% of the street-facing façade. 202 Rosemary involved 38.7% of the west street façade and 50.1% of the exterior-wall framing.
ARB approval can also lead to a separate board. 202 Rosemary later went to the Board of Adjustment as Case 2482, requesting three variances, covering lot coverage, floor area ratio and rear setback, for a storage shed attached to the main structure. That hearing was set for October 7, tabled to November 4 and rescheduled to December 2.
Delay notices go on the property and on the city's Public Notices page within three business days of Council action. That page's Demolition Delay Notice section currently has no entries.
The 2026 pattern continues through the end of the year. 431 Ogden Ln, filed by Uptmore Homes, and 126 Kennedy Ave, filed by Kana Homes, LLC, both ask to demolish 100% of the existing house and build a new single-family residence. Both were on the November 17 ARB agenda, and Council consideration is set for December 14. The code requires mailed notice to owners within 200 feet, and the full web packets are on the city's Public Notices page. Anyone curious about what is planned for their block can find it there before anything is built.
A posted notice on the property for at least 15 days, a notice on the city website and a mailed notice to owners within 200 feet. The city also suggests that applicants contact neighbors during conceptual design.
If you are pricing an older Alamo Heights house as a rebuild, or weighing whether to sell to a builder, the ARB calendar belongs in the plan from the first offer. The Meghan Pelley team can build those meeting dates into your offer terms and timeline. Start with a home valuation or a conversation through our Alamo Heights page.